What statutory protections apply if an off-plan property is delayed in Dubai?
- Jurisdiction
- Dubai; the Special Tribunal regime in Decree No. 33 of 2020 excludes projects within the DIFC (Art. 4)
- Review status
- Reviewed
- Last reviewed
- 2026-11-16
- Law stated as of
- 2026-11-16
Short answer
Dubai's off-plan legislation does not set a universal fixed late-handover payment. The position depends on the project's status and the contract. A buyer may ask the competent court to terminate the contract in the cases listed in Executive Council Resolution No. 6 of 2010, Art. 20. If RERA finally cancels the project, or the developer never commenced for a reason beyond its control without negligence or omission, the developer must refund the payments received.
Key points
- If the developer has not commenced work for a reason beyond its control and without negligence or omission on its part, or RERA cancels the project by a final reasoned decision, the developer must refund all purchaser payments (Law No. 13 of 2008, Art. 11(b), as replaced by Law No. 19 of 2020).
- A purchaser may ask the competent court to terminate the contract in the cases listed in Executive Council Resolution No. 6 of 2010, Art. 20, including a material specification change and serious construction defects at handover.
- After cancellation, RERA directs the escrow agent to refund within 14 days; if escrow funds are insufficient, the developer must pay the shortfall within 60 days, subject to the statutory extension mechanism (Resolution No. 6 of 2010, Arts. 25–26).
- The DLD may attempt conciliation between developer and purchaser, and a settlement approved by the DLD binds the parties (Resolution No. 6 of 2010, Art. 14).
- Decree No. 33 of 2020 applies to unfinished and cancelled projects within its jurisdiction; an unfinished project is one whose construction commenced but was suspended (Art. 1), and the Decree excludes projects within the DIFC (Art. 4).
- This page covers Dubai's specific off-plan statutory protections; general contractual remedies under the Civil Transactions Law are outside its scope.
Analysis
Draft, pending legal review. We checked the official Dubai legislation and DLD material below on 16 November 2026. Where an official English translation differs from the Arabic legislation, the Arabic text prevails. This page is deliberately limited to Dubai's specific off-plan statutory protections and does not attempt to state every general contractual remedy.
What does the law say about ordinary delay?
The Dubai off-plan statutes cited on this page do not create a universal fixed payment for every period of late handover. The agreed handover date, any grace period and any contractual delay clause come from the sale and purchase agreement. General contractual remedies may also be relevant under the applicable Civil Transactions Law, but those remedies are outside this page's scope.
How is the buyer's money protected?
Under Dubai Law No. 8 of 2007, Art. 9, the project's escrow account is used for that project and the developer's creditors cannot attach the money in it (official law).
If an emergency prevents completion, Art. 15 requires the escrow agent, after consulting the DLD, to take measures that protect depositors by securing completion or refunding them. See how escrow protects off-plan buyers.
When can a buyer ask the court to terminate the contract?
Executive Council Resolution No. 6 of 2010, Art. 20 identifies cases in which a purchaser may apply to the competent court to terminate the contract (DLD legislation compilation). They include:
- the developer refuses, without a reason accepted by the DLD, to deliver the final sale contract;
- the developer refuses to link payments to the construction milestones proposed by RERA;
- the developer makes a material change to agreed specifications;
- the unit is unfit for use at handover because of serious construction defects; and
- another case justifies termination under the general rules of law.
The DLD FAQ states that the DLD itself does not terminate the sale contract at the purchaser's request; termination is a judicial matter where the law requires court intervention.
Can the DLD settle the dispute?
Yes. Resolution No. 6 of 2010, Art. 14 authorises the DLD to undertake conciliation efforts between the developer and purchaser and propose solutions. If an agreement is reached, recorded in writing and approved by the DLD, it becomes binding on the parties.
What happens if the project is cancelled or never commenced?
Under Art. 11(b) of Dubai Law No. 13 of 2008, as replaced by Dubai Law No. 19 of 2020, the developer must refund all payments received from purchasers in either of these cases (official amendment):
- the developer has not commenced work for a reason beyond its control, without negligence or omission on its part; or
- RERA cancels the project by a final, reasoned decision.
The same amended Article 11 preserves recourse to the court or arbitration in the circumstances stated by Art. 11(g).
What are the cancellation-refund periods?
After project cancellation, Resolution No. 6 of 2010, Art. 25 provides for RERA to request the escrow agent to return purchaser funds within 14 days of cancellation.
Where the escrow account is insufficient, Art. 26 requires the developer to pay the purchasers within 60 days from the cancellation decision, with the extension mechanism stated by the article. Art. 27 addresses the steps where the developer does not comply.
These are statutory cancellation/liquidation periods. They are not a general deadline for compensation for ordinary late handover.
Which projects go to the Special Tribunal?
Dubai Decree No. 33 of 2020 governs the Special Tribunal for Unfinished and Cancelled Real Property Projects within the Decree's jurisdiction (official Decree).
- An Unfinished Real Property Project is a project whose construction commenced but was suspended for any reason (Art. 1).
- The Decree applies to the categories identified in Art. 4 and expressly excludes projects within the DIFC.
- The Tribunal's jurisdiction and powers are set out in Art. 6.
- Art. 10 restricts other Dubai courts and judicial entities from considering matters that fall within the Tribunal's jurisdiction and addresses transfer of existing/execution matters.
A project that is merely late but continues construction is not automatically an “Unfinished Real Property Project” under that definition.
Project-status information
The DLD FAQ refers users to DLD services for tracking project status and completion. Because service names and interfaces can change, this page does not reproduce a fixed technical-report fee.
General information
This page provides general information about Dubai's off-plan statutory regime. It does not determine whether a particular delay amounts to breach or whether a contract will be terminated.
Official sources
- Dubai Law No. 13 of 2008 Regulating the Interim Real Property Register (Art. 11), as amended
- Dubai Law No. 19 of 2020 amending Law No. 13 of 2008 (replacement Art. 11)
- Dubai Law No. 8 of 2007 Concerning Escrow Accounts for Real Estate Development (Arts. 9, 15)
- Executive Council Resolution No. 6 of 2010 — Implementing Bylaw of Law No. 13 of 2008 (Arts. 14, 20–27)
- Dubai Decree No. 33 of 2020 Concerning the Special Tribunal for Unfinished and Cancelled Real Property Projects (Arts. 1, 4, 6, 10)
- Dubai Land Department — Frequently asked questions